Project Highlights

Gallery

Construction Images

Nirvana
Cluster-12 (Row House No. 221-228) Foundation work completed for unit no. 221 to 227. 1st floor slab casting of 221 to 225 has been completed. Brickwork up to roof is in progress (06.10.21)
Nirvana
Cluster-13 (Row House No. 216-220) Foundation work & 1st floor slab is completed for unit no. 216 to 220. Brickwork up to roof in progress (06.10.21)
Nirvana
Cluster-14 (Row House No. 199-210) Foundation/Ground floor slab casting, 1st floor slab casting and Roof slab casting of row house no. of 199 to 210 has been completed. Finishing work in progress (06.10.21)
Nirvana
Cluster-15 (Row House No. 211-215) Foundation/Ground floor slab casting, 1st floor slab casting and Roof slab casting of row house no. of 211 to 215 has been completed. Finishing work in progress (06.10.21)
Nirvana
Cluster-16 (Row House No. 187-198) Foundation/ Ground floor slab casting, 1st floor slab casting and Roof slab of 187 to 191 has been completed. Finishing work in progress for the mentioned row house no (06.10.21)
Nirvana
Cluster-17 (Row House No. 178-186) Foundation has been completed. 1st floor slab of 178 to 186 has been completed. Roof slab of 178, 179 & 180 also completed. Brickwork, above roof work & plastering work in progress (06.10.21)
Nirvana
Cluster-19 (Row House No. 163-167) Foundation work, 1st floor slab casting and Roof slab of 163 to 167 has been completed. Above roof work & plastering work in progress (06.10.21)
Nirvana
Cluster-20 (Row House No. 168-177) Foundation, 1st floor slab and roof casting of 168 to 175 has been completed. Finishing work in progress for the above mentioned unit no (06.10.21)
Nirvana
Cluster-22 (Row House No. 148-152) Foundation work, 1st floor slab casting and Roof slab casting of unit no. 148 to 152 has been completed. Above roof work in progress (06.10.21)
Nirvana
Cluster-23 (Row House No. 138-147) Foundation, 1st floor slab and roof slab casting of 140 to 147 has been completed. Finishing work in progress for the above mentioned unit no (06.10.21)
Nirvana
Cluster 26 (Row House No. 118-127) Foundation/Ground floor slab casting, 1st floor slab casting, Roof slab casting and Brick work of unit no. of 122 to 127 has been completed (06.10.21)
Nirvana
Cluster 27 (Row House No. 107-115) Foundation/Ground floor slab casting, 1st floor slab casting, Roof Slab casting and Brick Work of unit no. 107 to 111 has been completed (06.10.21)
Nirvana
Cluster-28 (Row House No. 128-137) Foundation, 1st floor and roof slab casting of unit no. 128 to 135 has been completed. Finishing work in progress for the above mentioned unit (06.10.21)
Nirvana
Cluster-29 (Row House No. 98-106) Foundation work, 1st floor slab and Roof slab casting of row house no. of 101 to 106 has been completed (06.10.21)
Nirvana
Cluster-33 (Row House No. 71-81) Foundation/Ground floor slab casting has been completed, 1st floor slab and Roof slab casting of row house no. of 71 to 81 has been completed (06.10.21)
Nirvana
Cluster-34 (Row House No. 53-64) Foundation/Ground floor slab casting, 1st floor slab casting, Roof slab casting and Brick work of unit no. of 53 to 64 has been completed. Finishing work in progress (06.10.21)
Nirvana
Cluster-35 (Row House No. 82-90) Foundation, 1st floor slab & Roof slab casting has been completed for unit no. 82 to 84. Above roof work & plastering work in progress for the mentioned row house no (06.10.21)
Nirvana
Cluster-36 (Row House No. 43-52) Foundation, 1st floor slab & Roof slab casting of row house no. 49 to 52 is completed. Above roof work and plastering in progress for the mentioned row house no (06.10.21)
Nirvana
Cluster-39 (Row House No. 1-11) Foundation work, 1st floor slab casting and Roof slab casting of row house no. of 1 to 11 has been completed. Finishing work in progress (06.10.21)

Why you should choose this property ?

  • Skylight Roof for more natural light inside.

  • 96% to 100% light in each house.

  • Less than apartment price with ZERO super built up price.

  • Car parking attached to your doorstep.

  • Optimised window to carpet area ratio for more fresh air.